Page title

Project name

Report data dates: 19/05/2019 - 28/08/2019

Schedule Logic Analysis

Info

Comparison Last Period

01/08/2020 09/01/2020 Difference
Project Complete
04/09/2021
Project Complete
04/09/2021
42 Days
Project Complete
04/09/2021
Project Complete
04/09/2021
4%

Critical Paths

Info
Critical Pathes TF
Cement Works & Kitchen Floor 4
-50
Cement Works & Kitchen Floor 4
-50
Cement Works & Kitchen Floor 4
-50

Pas

Activity Analysis

Theme Criteria Actual Not Completed %
Critical Activities
- 3 - -
Start
14 3 8 42%
Finish
14 3 8 42%
Progress
14 3 8 42%

Project Status and Forecast

Info

Milestones

Info

Monthly Performence

Info
Actual Project % Complete 64%
Planned Project % Complete to Date 64%
Completion Pace
80%

Completion Forecast

Info
Monthly pace
80%
Original Duration
80%
Forecast month complete
80%
Project Delay
80%
Monthly % to complete on time
80%